File #: 24-3624    Version: 1 Name:
Type: Agenda Item Status: Consent Agenda
File created: 7/22/2024 In control: City Council
On agenda: 8/19/2024 Final action:
Title: Approval of an Amendment to the Agreement Between the City of Lewisville and Freese and Nichols for Landscape and Trail Design Services for Hebron Parkway Medians, Screening Wall and Trail; Adding Eight Months to the Project Timeline and $50,000 to the initial Agreement in the Amount of $104,349, for a Total of $154,349; and Authorization for the City Manager, or Her Designee, to Execute the Agreement.
Attachments: 1. Staff Memo - Amendment #1 Hebron Parkway Median Screening Wall and Trail - 2024.08.pdf, 2. ATTACHMENT A - Amendment 1 - 2024.08.14, 3. ATTACHMENT B - F&N Executed PSA_Hebron Parkway - 2024.08.14, 4. ATTACHMENT C -2018 Presentation Hebron Parkway - 2024.08.14, 5. ATTACHMENT D - Project Map - 2024.08.14, 6. Exhibit 1 ATTACHMENT A_Scope- 2024.08.14, 7. Exhibit 2 ATTACHMENT A_Updated Timeline- 2024.08.14, 8. Hebron Pkwy - Proposed Planting Plan and Trail Alignment_2024.08.14
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Approval of an Amendment to the Agreement Between the City of Lewisville and Freese and Nichols for Landscape and Trail Design Services for Hebron Parkway Medians, Screening Wall and Trail; Adding Eight Months to the Project Timeline and $50,000 to the initial Agreement in the Amount of $104,349, for a Total of $154,349; and Authorization for the City Manager, or Her Designee, to Execute the Agreement.

 

request

ADMINISTRATIVE COMMENTS:

 

In July 2023, the City Council approved a Professional Services Agreement (PSA) with Freese and Nichols, Inc. for design services for a median and right-of-way landscape improvements and a 12’ hike and bike trail along the northside of Hebron Parkway. Freese and Nichols must perform additional analysis, coordination and field work beyond the scope of the executed PSA to address Corridor Development Certificate (CDC) requirements. The additional services to be rendered include developing a revised CDC, completing hydraulic modeling, evaluating water surface elevation and velocity changes, and coordinating meetings with the US Army Corps of Engineers. These additional services and Oncor-directed modifications will extend the design period eight months to November 2024. Funding is available in the Hebron Parkway Streetscaping and Hike and Bike Trail Projects.

 

RECOMMENDATION:

 

That the City Council approve the agreement and authorize the City Manager, or her designee, to execute the agreement as set forth in the caption above.