Title: Approval of a Bid Award for CDBG Program Year 2019 Morningside Sewer Manhole and Sewer Main Line Rehabilitation Project to Canary Construction Company, Lewisville, Texas, in the Amount of $543,737.25; and Authorization for the City Manager to Execute the Contract.
Attachments: 1. Staff Memo, 2. Purchasing Memo, 3. CDBG funding memo, 4. Bid Tab, 5. Contract, 6. Contract Exhibit A, 7. Contract Exhibit B, 8. Contract Exhbit C, 9. Morning Side Map 1, 10. Morning Side Map 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Approval of a Bid Award for CDBG Program Year 2019 Morningside Sewer Manhole and Sewer Main Line Rehabilitation Project to Canary Construction Company, Lewisville, Texas, in the Amount of $543,737.25; and Authorization for the City Manager to Execute the Contract.

 

request

ADMINISTRATIVE COMMENTS:

 

A total of thirty-two (32) bid invitations were downloaded from Bidsync.com.  Two (2) bids were received and opened December 19, 2019.  This project consists of the rehabilitation of approximately 1,100 feet of 6 and 8-inch sanitary sewer lines in north Lewisville roughly bounded by Jones St. to the north, Valley Ridge Blvd. to the south, Mill St. to the west and Cowan Ave. to the east.  In addition to the line work, the project also includes new manhole installations as well as rehabilitation of existing manholes.  Funding for this project in the amount of $514,222 is available in the CDBG accounts, and the remainder of funds are available in the Miscellaneous Water and Sewer Line Repair Capital Project.

 

RECOMMENDATION:

 

That the City Council approve the award as set forth in the caption above and authorize the City Manager to execute the agreement.