title
Approval of Change Order #6 for Corporate Drive Segments 2 & 3 Project for a Reduction in the Amount of $1,393,226.43 and Authorize the City Manager, or Her Designee, to Execute the Change Order.
request
ADMINISTRATIVE COMMENTS:
On December 4, 2023, City Council approved the construction agreement with Sundt Construction Inc. for $40,990,000 and work began in February 2024. While the project was under construction, the City Council approved the Midway Branch Force Main Project which was designed to run along the Corporate Drive multipurpose trail. To preserve trees on City Park property (the Duwe property), the alignment was shifted into the Corporate Drive right-of-way creating a conflict with Sundt’s ability to finish the bridge water line and the multipurpose trail in Segment 3. Staff and Sundt recommend removing these remaining items from this specific contract and incorporating them into Corporate Drive Segments 4 & 5, which is currently under construction by Sundt. Therefore, Change Order #6 results in a reduction of $1,393,226.43.
RECOMMENDATION:
That the City Council approve the change order and authorize the City Manager, or her designee, to execute the change order as set forth in the caption above.