Title: Approval of a Contract Award for Construction Services for the Corporate Drive Segments 2 and 3 Project to Sundt Construction, Inc., Irving, TX, in the Amount of $43,039,500 and Authorization for the City Manager, or Her Designee, to Execute the Contract.
Attachments: 1. Corporate Drive Segments 2 and 3 - Staff Memo - 23.12.pdf, 2. Corporate Drive Segments 2 and 3 - Purchasing Memo - 23.12.pdf, 3. Corporate Drive Segments 2 and 3 - Evaluation Matrix - 23.12.04, 4. Corporate Drive Segments 2 and 3 - Signed Agreement - 23.12 (1), 5. Corporate Drive Segments 2 and 3 - Exhibit A - 23.12.04, 6. Corporate Drive Segments 2 and 3 - Exhibit B - 23.12.04, 7. Corporate Drive Segments 2 and 3 - Exhibit C - 23.12.04, 8. Corporate Drive Segments 2 and 3 - Corporate-Segment 2 and Segment 3 Map - 23.12.04
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Approval of a Contract Award for Construction Services for the Corporate Drive Segments 2 and 3 Project to Sundt Construction, Inc., Irving, TX, in the Amount of $43,039,500 and Authorization for the City Manager, or Her Designee, to Execute the Contract.

 

request

ADMINISTRATIVE COMMENTS:

 

A total of eighty-two (82) requests for proposals were downloaded from Bonfire. Four (4) proposals were received and opened on November 15, 2023.  An evaluation of proposals was performed, and it was determined that Sundt Construction, Inc. offered the best value for the City to complete work at Corporate Drive Segments 2 & 3 and is being recommended for award.  Funding for these services is available in the Corporate Drive capital projects. 

 

RECOMMENDATION

 

That the City Council approve the award and authorize the City Manager, or her designee, to execute the contract as set forth in the caption above.