Title: Approval of a Professional Services Agreement with RJN, Inc. for an Amount Not to Exceed $794,000 for the Timber Creek Pump Station Interceptor Sewer Design; and Authorization for the City Manager to Execute the Agreement.
Attachments: 1. Staff Memo, 2. Lewisville_Timber_Creek_Rehab_Exhibit, 3. Conceptual OPCC, 4. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Approval of a Professional Services Agreement with RJN, Inc. for an Amount Not to Exceed $794,000 for the Timber Creek Pump Station Interceptor Sewer Design; and Authorization for the City Manager to Execute the Agreement.

 

request

ADMINISTRATIVE COMMENTS:

 

The Timber Creek Interceptor Sewer consists of approximately 8,400 linear feet of 36- and 42-inch steel and clay pipe that begins west of the Timber Creek Pump Station near Railroad Street, continuing along the north side of Timber Creek and ending on the east side of Business SH121 south of the intersection of E. Southwest Parkway and has reached the end of its life cycle. According to as-built drawings, the Timber Creek Trunk Sewer was constructed in 1978. The professional services agreement includes condition assessment of the sanitary sewer using multi-sensor pipeline inspection (MSI) to determine recommended rehabilitation methods, conceptual (30%), preliminary (60%), final (90%) design, and construction (100%) drawings and specifications for approximately 8,400 LF of 36- and 42-inch sanitary sewer pipe, and surveying, geotechnical engineering services, and permitting services. Funding is available in the Timbercreek Capital Project.

 

RECOMMENDATION:

 

That the City Council approve the agreement as set forth in the caption above; and authorize the City Manager to execute the agreement.