File #: 24-3398    Version: 1 Name:
Type: Agreement/Contract Status: Consent Agenda
File created: 3/18/2024 In control: City Council
On agenda: 4/1/2024 Final action:
Title: Approval of a Construction Manager at Risk (CMAR) Pre-construction Agreement with Archer Western Construction, LLC., Irving, Texas, in the Amount of $449,814 for the Prairie Creek Wastewater Treatment Plant Aeration Basin Expansion Project; and Authorization for the City Manager, or her Designee, to Execute the Agreement.
Attachments: 1. Prairie Creek Wastewater Treatment Plant II (PCWWTP) Aeration Basin Expansion - Staff Memo - 24.04.pdf, 2. Prairie Creek Wastewater Treatment Plant II (PCWWTP) Aeration Basin Expansion- Signed Agreement-24.04.01, 3. Prairie Creek Wastewater Treatment Plant II (PCWWTP) Aeration Basin Expansion - Maps - 24.04.01
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Approval of a Construction Manager at Risk (CMAR) Pre-construction Agreement with Archer Western Construction, LLC., Irving, Texas, in the Amount of $449,814 for the Prairie Creek Wastewater Treatment Plant Aeration Basin Expansion Project; and Authorization for the City Manager, or her Designee, to Execute the Agreement.

request

 

ADMINISTRATIVE COMMENTS:

 

In April 2022, the City Council approved the professional service agreement with a design consultant for design, bidding, and construction phase services for the expansion of the aeration basin and blower system improvements. The preliminary design report 30% deliverable indicated schedule constraints and procurement delays and staff has decided to utilize the Construction Manager at Risk (CMAR) delivery method to best mitigate these issues during construction. Through the RFQ/RFP process, staff has selected Archer Western as the CMAR for this project.

 

RECOMMENDATION:

 

That the City Council approve the agreement and authorize the City Manager, or her designee, to execute the agreement as set forth in the caption above.